Project:  California Blvd. Right Turn Lane at Fair Oaks
Contractor:
Ranco Corporation

Start Date:
October 18, 2004

Completion Date:
December 2004

Description of Work:
Widening the south side of California Blvd. from approximately 300 feet west of Fair Oaks Ave. to Fair Oaks Ave.  Providing a right turn lane for eastbound California Blvd. to southbound Fair Oaks Ave.

 

California Blvd. Right Turn Lane at Fair Oaks
California Blvd. Right Turn Lane at Fair Oaks

View Project

Project:  SR 110 to I 210 Connector/Marengo Interchange Emphasis
Contractor:
Chrisp Company

Start Date:
November 15, 2004

Completion Date:
December, 2004

Description of Work:
Striping modifications at various intersections and installation of directional signs.

 




 

SR 110 to I210 Connector / Marengo Interchange Emphasis
SR 110 to I210 Connector / Marengo Interchange Emphasis
SR 110 to I210 Connector / Marengo Interchange Emphasis

View Project

Project:  Lake Avenue/Walnut Street Intersection Mobility Improvements
Contractor:
EC Construction

Start Date:
May 2006

Completion Date:
September 2006

Description of Work:
Widen the east side of Lake Avenue, from Walnut Street to approximately 300 feet south to provide a right turn lane from northbound Lake Avenue to eastbound Walnut Street

Lake Avenue/Walnut Street Intersection Mobility Improvements

 

 

 

 


Lake Avenue/Walnut Street Intersection Mobility Improvements

View Project

Project:  Raymond Ave. to SR110 Connector
Contractor:
Los Angeles Engineering

Start Date:
June 2005

Completion Date:
May 2007

Description of Work:
Widen Glenarm St between Fair Oaks Ave and SR 110.  Construct an at-grade on-ramp from eastbound Glenarm St to southbound SR 110.  Widen SR 110 to provide a merging lane.

Raymond - SR710 Connector

 

 

 

 


Raymond - SR710 Connector

View Project

Project:  California Blvd. Right Turn at Raymond

Contractor:
Sully-Miller Contracting Co.

Start Date:
January 2007

Completion Date:
June 2007

Description of Work:
Widen the north side of California Boulevard from Arroyo Parkway to Raymond Avenue to provide a right turn lane from westbound California Boulevard to northbound Raymond Avenue.

California at Raymond











California at Raymond

View Project

Project:  Raymond Ave. Widening

Contractor:
Sully-Miller Contracting Co.

Start Date:
September 2006

Completion Date:
July 2007

Description of Work:
Widen Raymond Avenue from 56 feet to 60 feet between Del Mar Boulevard and Glenarm Street, which will provide four through-travel lanes and left turn lanes at several intersections.

Raymond Widening

 

 


 




Raymond Widening

View Project

 