Night Work - Fair Oaks Ave - Holly to Union 9-28 to 10-2

Full Panel Replacement on Fair Oaks Avenue - Schedule

Phase 1 (Monday Evening)

11:00 PM - 12:00 AM  Setup Traffic Control
11:30 PM - 2:00 AM Demolition of Phase 1 
2:00 AM - 3:00 AM Grading of Phase 1 
3:00 AM - 7:00 PM Pourback & Finish Phase 1
7:00 AM - 8:00 AM  Cleanup and Traffic Control Pick Up
8:00 AM Open Road to Vehicular Traffic

Phase 2 (Tuesday Evening)

11:00 PM - 12:00 AM Setup Traffic Control
11:30 PM - 2:00 AM Demolition of Phase 2
2:00 AM - 3:00 AM Grading of Phase 2
3:00 AM - 7:00 PM Pourback & Finish Phase 2
7:00 AM - 8:00 AM Cleanup and Traffic Control Pick up
8:00 AM Open Road to Vehicular Traffic

Phase 3 (Wednesday Evening)

11:00 PM - 12:00 AM Setup Traffic Control
11:30 PM - 2:00 AM Demolition of Phase 3
2:00 AM - 3:00 AM Grading of Phase 3
3:00 AM - 7:00 PM Pourback & Finish Phase 3
7:00 AM - 8:00 AM  Cleanup and Traffic Control Pick UP
8:00 AM  Open Road to Vehicular Traffic

Phase 4 (Thursday Evening)

11:00 PM - 12:00 AM Setup Traffic Control
11:30 PM - 2:00 AM  Demolition of Phase 4
2:00 AM - 3:00 AM  Grading of phase 4
3:00 AM - 7:00 PM Pourback & Finish Phase 4
7:00 AM - 8:00 AM Cleanup and Traffic Control Pick Up
8:00 AM Open Road to Vehicular Traffic