Pasadena Public Works will be completing the Orange Grove Blvd. resurfacing project over the course of the next several weeks.
What to expect: Work and impact will vary by section (see color coded map and descriptions below)
Blue Area
Pavement will be recycled and topped with asphalt surface.
Sep. 10 to 23* - Cold In Place Recycling - Road and driveways will be open with moving closures as surface placement is completed.**
Sep. 29 to Oct. 06* - Final Rubberized Asphalt Paving
Road and driveways will be open with moving closures as surface placement is completed.**
Yellow Area
Curbs and ramps will be constructed, existing asphalt will be milled and topped with new asphalt surface
Sep. 08 to Oct. 26* - Concrete Curb, Gutter, & Ramp Replacement
Road and driveways will be open with moving closures as work is completed. Some driveway use may be restricted during working hours.**
Oct. 26 to Nov. 06* - Final Rubberized Asphalt Paving
Road and driveways will be open with moving closures as surface placement is completed.**
*Dates Provided are approximate and subject to change. For most accurate information residents and businesses should watch for temporary "No Parking" signs which will be placed a minimum of 48 hours in advance
**Overnight Parking Permits for parking on adjacent streets will be provided, as needed, for driveway and other access impacts. Please place trash receptacles at the curb prior to 7 am on your regularly scheduled collection day
Questions? Contact
Contractor - (951) 545-9691
Public Works - (626) 744-4268
Project Inspector - (626) 744-7594