Project Description
The Department of Public Works is initiating the resurfacing of Fair Oaks Avenue, extending from Washington Boulevard to just north of Montana Street, along the City/County jurisdictional boundary, and Madison Ave, from Orange Grove Blvd to Villa St.
Justification
This effort follows the completion of Pasadena Water and Power’s (PWP) Fair Oaks Water Main Replacement Project in March 2025. That project required extensive trenching along Fair Oaks Avenue to replace two aging water mains that had been in service for nearly a decade. For more information regarding PWP project visit: Fair Oaks Water Main Replacement Project
Due to the high cost of restoring the trench cuts in the predominantly concrete roadway, PWP and the Department of Public Works explored a more cost-effective and comprehensive solution. Rather than just repairing the trench, the City opted to resurface the entire roadway width, meeting restoration needs and improving overall pavement conditions within a similar budget.
In addition, based on community input and in collaboration with the Department of Transportation (DOT), the City is evaluating a lane reconfiguration along this stretch of Fair Oaks Avenue. For more information and status of the lane reconfiguration, please visit: North Fair Oaks Safety Project
To maximize efficiency and cost savings, pavement restoration on Madison Avenue (from Villa Street to Orange Grove Boulevard) has also been included as an alternate bid item.
Scope
Trench repair and full-width pavement resurfacing with new material, curb and gutter repairs, curb ramp improvements, utility adjustments, updated roadway striping and layout modifications
Schedule
Construction Start: October 20, 2025
Anticipated Completion: February 2026
| Type of Work (Fair Oaks Ave) | From | To | What to Expect |
|---|---|---|---|
| Concrete Repair | 10/20/2025 | 11/07/2025 | No Parking signs |
| Remove & Replace Pavement* | 11/10/2025 | 1/31/2026 | No Parking signs Travel Lane Closure Potential Transit Detour to N Raymond Ave |
| Modified Striping Layout | 12/19/2025 | 12/24/2025 | No Parking signs |
| Remaining Work | 12/19/2025 | 1/31/2026 | No Parking signs |
*modified due to precipitation forecast
| Type of Work (Madison Ave) | Date | What to Expect |
|---|---|---|
| Concrete Repair | 12/05/2025 | No Parking signs |
| Remove & Replace Pavement * | 12/10/2025 | No Parking signs |
| Remove & Replace Pavement * | 12/15/2025 | No Parking signs Travel Lane Closure |
| Remaining Work | 12/19/2025 | No Parking signs |
This schedule is subject to change
What to Expect
Please expect delay during the construction hours and temporary road and lane closure in some areas.
Please follow posted signs and detour routes. More updates will be shared via the City’s social media channels and on this webpage.
Transit
For information how the project will impact the transit route please contact general phone number for Pasadena Transit is (626) 744-4055 or visit the Pasadena Transit App.
Funding
Funded through Pasadena Water and Power trench restoration funds and supplemental funding from the Public Works Annual Citywide Street Resurfacing Program.
Contact
Prime Contractor: Toro Enterprises, Inc
Public Works Engineer/ Project Manager: Roya Falahati: (626) 744-3711 or rfalahati@cityofpasadena.net.