March 2016 La Loma Bridge Project Update

Pile driving operation at the west abutment is complete and the contractor will soon move to the east side of the structure to begin construction of the east abutment adjacent to South Arroyo Blvd. In order to accommodate this work, the bridge plans include a temporary lane shift and slight lane width reduction for both the northbound and southbound lanes of South Arroyo Blvd at the intersection with La Loma Rd. This shift in traffic will extend to near completion of the project. These changes are not expected to adversely affect traffic flow or to otherwise create traffic delays.

Project Progress Photos For March 2016

Bridge Overview
Bridge Overview
Building Panels for Exterior Girder Forms Across Bridge
Building Panels for Exterior Girder Forms Across Bridge
Formation of Pier Columns
Formation of Pier Columns