May 2016 La Loma Bridge Project Update

Construction of the west abutment and retaining wall at the west abutment was completed. Forming and steel placement for the mid-span exterior girders was completed and concrete was placed completing these portions of the exterior architectural girders. Formation of the remaining portions of the exterior girders continued.

Project Progress Photos For May 2016

Nearly completed with forms for the exterior girder spandrel arch between Piers 2 and 4
Nearly completed with forms for the exterior girder spandrel arch between Piers 2 and 4
Building retaining wall forms at abut #1
Building retaining wall forms at abut #1