October 2016 La Loma Bridge Project Update

The stem and soffit pour occurred on October 3, 2016. Work for the month of October will include stripping forms from the stem and soffit, placing utilities within the bridge's box girder bays, and placing formwork and reinforcing steel for the bridge deck (driving surface of the bridge).