December 2015 La Loma Bridge Project Update

December 2015 Construction of the temporary sewer bypass is currently underway. The contractor will mobilize equipment in preparation for demolition of the existing bridge in late December and continue through January 2016. Demolition of the existing bridge will begin January 4, 2016. Project Progress Photos For December 2015 A view of North side of bridge, looking West, depicting the placement of aluminum joist, from falsework bent, westward, over cantilever transverse beams. A view of the Southern outer cantilever soffit platform,... continue reading »"December 2015 La Loma Bridge Project Update"

November 2015 La Loma Bridge Project Update

November 2015 A majority of the work continues below the bridge for the next couple of months. The contractor has been erecting vertical elements of the falsework. The trail on the east side of the channel under the bridge will be closed intermittently between 7 a.m. to 4 p.m., Monday - Friday, from mid-October 2015 (while constructing overhead elements) through December 2015 (during removal of existing bridge). Signs will be posted designating a detour trail route. Preparations to construct a... continue reading »"November 2015 La Loma Bridge Project Update"

October 2015 La Loma Bridge Project Update

October 2015 The asphalt concrete has been removed from the bridge deck. A majority of the work is occurring below the bridge. A pedestrian cover and support foundations for the “falsework” that will be constructed are underway. The contractor has begun erecting the vertical elements of the falsework. The trail on the east side of the channel under the bridge will be closed intermittently between 7 a.m. to 4 p.m., Monday - Friday, from mid-October 2015 (while constructing overhead elements) through... continue reading »"October 2015 La Loma Bridge Project Update"

September 2015 La Loma Bridge Project Update

September 2015 Pasadena Water and Power Department completed the power main and vault relocation efforts on La Loma Road.  The City is coordinating remaining utility relocations. Traffic has been detoured to other bridges across the Arroyo Seco.  Motorists are able to cross using the Colorado Boulevard Bridge to access areas north of La Loma Bridge, and are able to use the San Rafael Bridge to access areas south of La Loma Bridge.  The Department of Public Works has created a... continue reading »"September 2015 La Loma Bridge Project Update"