On June 17, 2024, the City of Pasadena awarded the Annual Citywide Street Resurfacing and ADA Improvement Program, FY 2024 Project. The construction is scheduled to commence on August 26, 2024 through February 2025.
Project Description
The construction of the Fiscal Year (FY) 2024 Annual Citywide Street Resurfacing Project is scheduled to commence on August 26 with the anticipated completion by early February 2025. This project will construct up to 44 streets covering ten centerline miles of asphalt pavement, including two miles of asphalt overlay and/or pavement reconstruction, and eight miles of pavement preventative maintenance (microsurfacing).
The street resurfacing project includes replacement of uplifted curb and gutter, sidewalk, and installation of new curb ramps, adjustment of existing utility manholes, replacement of signal loop detectors; and installation of striping and raised pavement markers.
Justification:
This project is consistent with the City Council’s goals to improve, maintain and enhance public facilities and infrastructure, and to improve mobility and accessibility throughout the City. It also supports the Public Facilities Element of the General Plan by maintaining public facilities to enhance the quality of life of the community.
Additionally, the systematic resurfacing at regular intervals prolongs the service life of roadway pavement, and significantly lowers the cost of maintaining paved public streets by reducing the need for full reconstruction.
Environmental Analysis:
On June 17, 2024, City Council found the project herein to be categorically exempt under the California Environmental Quality Act (CEQA) Guidelines in accordance with Title 14, Chapter 3, Article 19, Section 15301, Class 1, and Section 15303, Class 3, Class 1 consists of minor alterations of existing facilities involving negligible or no expansion of use. Class 3 consists of construction of limited number of new, small facilities or structures. There would be no expansion of use of the street network as a result of the project, and therefore, there are no unusual circumstances.
Funding:
This project is primarily be utilizing the remaining funds from the City Councils’ one-time $5.4 million additional appropriation of General Fund (American Rescue Plan Act - ARPA) in FY 2024.
Contact:
Ryan Lim – Project Manager
Please contact the Public Works Engineering Division at (626) 744-4336 or rlim@cityofpasadena.net.